Which statement describes the relationship between Manage Quality process and Control Quality process?
A.
Manage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
B.
Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.
C.
Manage Quality and Control Quality are the same.
D.
Manage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.
Why the other options are incorrect:
B. This reverses the definitions of Manage and Control Quality.
C. They are not the same; they have different focus areas (process vs. product).
D. Control Quality is not part of Stakeholder Management; it belongs to Project Quality Management.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 1 week agotheplaceholder
11 months, 1 week agoMoonManBlue
3 years, 9 months ago