exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 108 discussion

Actual exam question from PMI's CAPM
Question #: 108
Topic #: 1
[All CAPM Questions]

What are the inputs of the Estimate Costs process?

  • A. Project management plan, work performance data, enterprise environmental factors, and organizational process assets
  • B. Project management plan, project documents, enterprise environmental factors, and organizational process assets
  • C. Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
  • D. Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CalvinthePM
1 year, 2 months ago
It's B. Each of the other choices contains an output of other processes. Work performance Data is an input of Control Cost.
upvoted 1 times
pahkhu
10 months, 1 week ago
and basis of estimates is an input of Determine Budget process.
upvoted 1 times
...
...
MFrankieG2022
1 year, 4 months ago
list of answers are not great...
upvoted 2 times
...
MoonManBlue
3 years, 8 months ago
B-PMP, Project Docs, OPA's, and EEF's-7.2
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...