Question #: 175
Topic #: 1
[All CAPM Questions]

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

  • A. What-if scenario analysis
  • B. Simulation
  • C. Alternatives analysis
  • D. Reserve analysis
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
11 months, 3 weeks ago
D. Reserve analysis When a project manager is determining the amount of contingency needed for a project, they are using "reserve analysis." Reserve analysis involves assessing and allocating contingency reserves to account for uncertainties and risks in the project. Contingency reserves are additional funds or time that are set aside to address unforeseen events or risks that may impact the project.
upvoted 1 times
...
MoonManBlue
4 years, 2 months ago
D-Reserve Analysis 6.4.2.6
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.