A. Project charter and requirements documentation
❌ Requirements documentation is an output, not an input.
B. Project charter and business documents
✅ Correct. These are both valid inputs to the Collect Requirements process.
C. Project charter and stakeholder requirements
❌ Stakeholder requirements are gathered during this process, not before it.
D. Business documents and requirements traceability matrix
❌ The requirements traceability matrix is an output, not an input.
B. Project charter and business documents
The inputs to the Collect Requirements process typically include the project charter and various business documents. The project charter provides the project manager with high-level information about the project, its objectives, and its stakeholders. Business documents may include documents related to the business case, business requirements, and other relevant information that helps in understanding the business needs and requirements of the project. These inputs are essential for collecting and documenting the project's requirements effectively.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 week, 2 days ago041ba31
1 year agoMoonManBlue
4 years, 3 months ago