Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

  • A. List of identified risks, potential risk owners, list of potential risk response
  • B. List of identified risks, list of causes, list of risk categories
  • C. Short risk titles, list of potential risk owners, list of impacts on objectives
  • D. List of activities affected, list of potential risk responses, list of causes
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
7 months, 1 week ago
A-List of identified risks, Potential risk owners, and potential risk responses 11.2.3.1
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago