When the Identify Risks process is completed (as per PMBOK Guide), the risk register is created or updated to include, at a minimum:
✅ List of identified risks
✅ Potential risk owners (optional in early phases, but ideally included)
✅ Potential risk responses
Other common entries may include:
Risk descriptions
Root causes
Risk categories
Triggers
Impacts on project objectives (more detailed during risk analysis)
Why not the other choices?
B: Includes useful elements (causes, categories), but omits potential owners and responses, which are important outputs of the Identify Risks process.
C: Short titles and impacts are helpful, but risk responses are missing.
D: Activities affected and causes are relevant but identified risks themselves are not explicitly listed, and risk register is not structured by activities.
A-List of identified risks, Potential risk owners, and potential risk responses 11.2.3.1
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 week, 3 days agoJesseChou_123
1 week, 3 days agoMoonManBlue
9 months ago