Why the other options are incorrect:
B. ❌ ROI is a financial metric, not a tailoring factor. It's used for evaluating business value, not tailoring project management processes.
C.❌ Earned Value is a performance measurement tool, not a factor for tailoring methodology.
D.❌ SPI is used to measure schedule efficiency—not to determine how to tailor the project approach.
A. Company culture
Among the factors that could lead a project to be tailored, company culture plays a significant role. The company culture includes the values, norms, and behaviors that are prevalent within an organization. Depending on the organization's culture, certain project management processes, practices, and methodologies may need to be customized or tailored to align with the way the organization operates.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.