Actual exam question from PMI's CAPM
Question #: 192
Topic #: 1
[All CAPM Questions]

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration.
Which of the following activities is done first?

  • A. Create Work Breakdown Structure (WBS)
  • B. Create Scope Baseline
  • C. Collect Requirements
  • D. Define Scope
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 week ago
Selected Answer: C
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first? A. Create Work Breakdown Structure (WBS) B. Create Scope Baseline C. Collect Requirements D. Define Scope
upvoted 1 times
...
JesseChou_123
1 month ago
Selected Answer: C
In the context of an iteration-based or Agile project, at the beginning of each iteration (or sprint), the team: Identifies and clarifies the highest-priority backlog items (i.e., user stories or requirements). Determines what can be delivered in the iteration based on capacity and complexity. This corresponds to the "Collect Requirements" process in traditional project management, which involves: Gathering detailed information about what stakeholders need and expect from the project. Using tools such as interviews, focus groups, and facilitated workshops to understand and document requirements.
upvoted 1 times
...
theplaceholder
11 months ago
Selected Answer: C
Collect Requirements is performed at the start of each iteration in an adaptive/agile environment.
upvoted 1 times
...
wwgk1980
11 months, 3 weeks ago
C The overall scope of an adaptive project will be decomposed into a set of requirements and work to be performed, sometimes referred to as a product backlog. At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three processes (Collect Requirements, Define Scope, and Create WBS) are repeated for each iteration page 131
upvoted 1 times
...
bramirezb593
1 year, 1 month ago
Right answer is C: At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three processes (Collect Requirements, Define Scope, and Create WBS)
upvoted 2 times
...
adingmaki
1 year, 1 month ago
A product backlog is a prioritized list of work for the development team that is derived from the roadmap and its requirements. definse scope it is
upvoted 1 times
...
Hungdv
1 year, 4 months ago
Define scope
upvoted 1 times
...
meg002
1 year, 7 months ago
Selected Answer: C
In order to define the scope, the requirements of the stakeholders must be collected first.
upvoted 3 times
limoncello
1 year, 6 months ago
but its at the beginning of an iteration, I assume the requirements have been cllected already so it should be D
upvoted 3 times
theplaceholder
11 months ago
in an agile/adaptive project, the requirements would be collected during each iteration.
upvoted 3 times
...
...
...
MoonManBlue
3 years, 9 months ago
D-Define Scope p. 151
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...