Question #: 138
Topic #: 1
[All CAPM Questions]

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

  • A. Push communication
  • B. Pull communication
  • C. Interactive communication
  • D. Stakeholder communication
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
5 days, 15 hours ago
Selected Answer: B
Why the other options are incorrect: A. Push communication: This involves sending information directly to recipients, such as via email, newsletters, or reports — not applicable here. C. Interactive communication: This is two-way, real-time exchange like meetings, calls, or chats. D. Stakeholder communication: Not a communication method — this is a broad term that includes various communication strategies tailored to stakeholders.
upvoted 1 times
...
UlrichIng
8 months ago
Pull Communication
upvoted 3 times
...
MoonManBlue
8 months, 3 weeks ago
B-Pull Communication-10.1.2.5
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...