What is the first step in the Stakeholder Management process?

  • A. Plan Stakeholder Engagement
  • B. Identify Stakeholders
  • C. Manage Stakeholder Responsibility
  • D. Monitor Stakeholder Activity
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
7 months, 1 week ago
B-Identify Stakeholders-Chapter 13
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago