During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

  • A. Change request
  • B. Risk response
  • C. Risk management plan
  • D. Lessons learned
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 2 weeks ago
Selected Answer: A
During the execution phase, if a defect is found, repairing it typically involves a corrective action or defect repair—both of which must go through the Integrated Change Control process in most projects. This means the project manager must submit a change request. Let’s evaluate the choices: A. Change request ✅ Correct. Defect repairs are a type of change request. The project manager documented the issue and initiated actions to repair it, which aligns with submitting and implementing an approved change request. B. Risk response ❌ A risk response deals with potential issues (risks), not actual defects. A defect is an issue, not a risk. C. Risk management plan ❌ This is a planning document and does not describe the action taken during execution to fix a defect. D. Lessons learned ❌ These are captured during or after the project and do not refer to real-time problem resolution.
upvoted 1 times
...
Vangelis_1980
1 year ago
Selected Answer: A
A. Change request
upvoted 2 times
...
UlrichIng
4 years, 9 months ago
A. Change request
upvoted 2 times
...
MoonManBlue
4 years, 10 months ago
A-Change Request-5.5.3.3
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.