Exam CAPM topic 1 question 230 discussion

Actual exam question from PMI's CAPM
Question #: 230
Topic #: 1
[All CAPM Questions]

Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

  • A. Project Schedule Management
  • B. Project Scope Management
  • C. Project Resource Management
  • D. Project Integration Management
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 2 weeks ago
Selected Answer: D
Why not the others? A. Project Schedule Management: Focuses on creating and controlling the project schedule. B. Project Scope Management: Focuses on defining and controlling what is and is not included in the project. C. Project Resource Management: Deals with acquiring, managing, and leading the project team and other resources.
upvoted 1 times
...
theplaceholder
11 months, 3 weeks ago
Selected Answer: D
charter > PIM
upvoted 1 times
...
garlicbread
1 year ago
Selected Answer: D
Life cycles is part of the charter segment, I think
upvoted 1 times
...
Rocket20
1 year ago
Selected Answer: D
D. Integration Management
upvoted 1 times
...
pbbade
1 year, 3 months ago
Selected Answer: D
is the correct answer
upvoted 1 times
...
UlrichIng
3 years, 9 months ago
Project Integration Management
upvoted 3 times
...
MoonManBlue
3 years, 10 months ago
D-Project Integration Management p.74
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...