Actual exam question from PMI's CAPM
Question #: 187
Topic #: 1
[All CAPM Questions]

Which is the tool or technique that is used to obtain the list of activities from the work packages?

  • A. Data analysis
  • B. Leads and lags
  • C. Precedence diagramming method
  • D. Decomposition
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
1 year, 1 month ago
Selected Answer: D
D. Decomposition Decomposition is the tool or technique used to obtain the list of activities from the work packages. Decomposition involves breaking down the higher-level project components, such as deliverables or work packages, into smaller, more manageable activities or tasks. This process helps in defining the detailed work required to accomplish the project's objectives. The result of decomposition is a hierarchical structure of project activities, often represented in a Work Breakdown Structure (WBS), which provides a detailed list of activities derived from the work packages.
upvoted 1 times
...
MoonManBlue
4 years, 4 months ago
D-Decomposition
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.