D. Decomposition
Decomposition is the tool or technique used to obtain the list of activities from the work packages. Decomposition involves breaking down the higher-level project components, such as deliverables or work packages, into smaller, more manageable activities or tasks. This process helps in defining the detailed work required to accomplish the project's objectives. The result of decomposition is a hierarchical structure of project activities, often represented in a Work Breakdown Structure (WBS), which provides a detailed list of activities derived from the work packages.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.