Why the other options are incorrect:
A. Critical chain method: This is a scheduling technique focused on resource constraints and buffers, not the basic calculation of the critical path.
B. Graphical Evaluation and Review Technique (GERT) diagram: GERT is used for probabilistic network analysis with loops and branches, more complex than needed for typical critical path calculation.
C. Gantt chart: A Gantt chart shows the schedule timeline but does not explicitly show dependencies or help calculate the critical path directly.
D-Project Network Diagram is the best choice here, although they may be going for CCM, but that was removed from the current edition
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 4 weeks agotheplaceholder
11 months, 3 weeks agoMoonManBlue
3 years, 10 months ago