A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

  • A. Discussing with management
  • B. Escalating to the sponsors
  • C. Engaging regularly with stakeholders
  • D. Engaging only with decision makers
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
7 months, 1 week ago
C-Engaging Regularly with Stakeholders
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago