exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 172 discussion

Actual exam question from PMI's CAPM
Question #: 172
Topic #: 1
[All CAPM Questions]

Which of the following is used as an input to prepare a cost management plan?

  • A. Expert judgment
  • B. Lessons learned
  • C. Cost estimates
  • D. Project management plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 day, 19 hours ago
Selected Answer: D
Why other options are not inputs: A. Expert judgment: Expert judgment is a technique used in preparing the cost management plan, but it's not an input document itself. B. Lessons learned: Lessons learned from previous projects are a valuable source of information for refining cost management processes, but they are typically part of organizational process assets or project document updates, not a direct input to the initial preparation of the cost management plan. C. Cost estimates: Cost estimates are an output of the cost management planning process, not an input used to prepare the plan. The cost management plan lays out the methodology for producing those estimates.
upvoted 1 times
...
041ba31
1 year ago
Selected Answer: D
D. Project management plan The project management plan serves as an input to prepare a cost management plan. The cost management plan is a subsidiary plan within the overall project management plan. It outlines how project costs will be estimated, budgeted, monitored, and controlled throughout the project's lifecycle. Therefore, the project management plan provides the foundational information and framework for creating the cost management plan.
upvoted 1 times
...
Pradnyasachin
1 year ago
Selected Answer: D
The cost management plan is a subsidiary plan within the project management plan. It details how the project costs will be estimated, budgeted, managed, and controlled throughout the project lifecycle. The project management plan, which encompasses various subsidiary plans, provides the foundational information necessary to create specific management plans, such as the cost management plan.
upvoted 1 times
...
MoonManBlue
4 years, 2 months ago
D-Project Management Plan-7.1
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...