C - Overall, the customer and sponsor have a continuous and collaborative involvement in project scope management activities in adaptive or agile life cycles. Their active participation ensures that the project stays aligned with their needs and expectations.
Tricky question, manual says continuolsy engagement in deliverablees as they are created, and mention Validate and Control Scope which are the end of an iteration.
I think is D.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Amylsmith25
6 months, 1 week agotheplaceholder
8 months, 1 week agogarlicbread
9 months, 2 weeks agoadingmaki
11 months, 2 weeks agoMyriam_Andrea
1 year agoanfacer
1 year, 4 months agowencai002
2 years, 8 months agoMoonManBlue
3 years, 7 months ago