Project reporting is a tool that is most closely associated with which process?

  • A. Communicate Plan
  • B. Manage Communications
  • C. Report Performance
  • D. Control Communications
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
Let’s break down the options: A. Communicate Plan ❌ This is not a real PMI process name. Possibly a confusion with Plan Communications Management. B. Manage Communications ✅ This process is in the Executing Process Group. It ensures timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and disposition of project information. Project reporting (status reports, progress reports, etc.) is a key tool/technique here. C. Report Performance ❌ This was used in older PMBOK editions (PMBOK 4). It has since been replaced or merged into Monitor and Control Project Work and Manage Communications in newer editions (PMBOK 6 & 7). D. Control Communications ❌ This is about monitoring and controlling communications throughout the project lifecycle, not primarily focused on reporting.
upvoted 1 times
...
JesseChou_123
1 month, 4 weeks ago
Selected Answer: B
Why the others are incorrect: A. Communicate Plan Not a standard PMBOK process. This is likely a distractor. C. Report Performance This sounds logical but is not a formal PMBOK process. Performance reporting is part of communications and control processes, but not a standalone process. D. Control Communications Involves monitoring and controlling communication throughout the project lifecycle — making sure communications meet the plan, not generating the reports themselves.
upvoted 1 times
...
JesseChou_123
1 month, 4 weeks ago
Selected Answer: B
Why other options are incorrect: A. Communicate Plan: While a communication plan is an important part of project management, it's a plan for how to communicate, not the act of reporting performance itself. C. Report Performance: This is the output of the Manage Communications process, not the process itself. D. Control Communications: This process focuses on monitoring and controlling communications to ensure the information needs of stakeholders are met, not the creation and distribution of reports.
upvoted 1 times
...
Georgess123
10 months, 1 week ago
Manage Communications
upvoted 3 times
...
MoonManBlue
1 year, 4 months ago
B-Manage Communications
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...