Which statement describes the Monitor Communications process?

  • A. Evaluates the differences between the communications management plan and the reality of communications in a project
  • B. Ensures that the information needs of the project and the stakeholders are met
  • C. Ensures that project information is created, collected, and distributed in a timely and appropriate manner
  • D. Develops an appropriate and plan for communication of project activities
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
emilianogalati
9 months, 3 weeks ago
Selected Answer: B
Chap. 10.3 Monitor communications. pg. 388
upvoted 3 times
...
jesslhong
1 year ago
I think A should be the answer - key word being "evaluate" since it's about monitoring. A is broad enough to include the management processes of B & C. Chat GPT also says A.
upvoted 1 times
CraigB83
9 months, 2 weeks ago
if you push ChatGPT further on this: The correct answer in the context of the PMBOK Guide for the Monitor Communications process is: B. Ensures that the information needs of the project and the stakeholders are met. The Monitor Communications process is primarily concerned with overseeing and ensuring that the information needs of the project and its stakeholders are being addressed. This involves monitoring communication performance, understanding stakeholder communications requirements, and making adjustments to the communication plan as needed to meet those requirements.
upvoted 2 times
Dken
4 months, 2 weeks ago
Correct Answer is A The Monitor Communications process is part of the Monitoring and Controlling Process Group in Project Communications Management. This process ensures that the information needs of the project and its stakeholders are being met effectively. It involves tracking and reviewing project communications to ensure that the communication plan is being followed and that stakeholders are receiving the necessary information.
upvoted 1 times
Dken
4 months, 2 weeks ago
Sorry.. I meant B.. as you can see this process ENSURES THAT THE INFORMATION NEEDS OF THE PROJECT AND ITS STAKEHOLDERS ARE MET. Evaluating the differences between the communication plan and the actual communications is what you DO, but the final purpose is not to compare but to ensure
upvoted 1 times
...
...
...
...
MJVIS
1 year, 3 months ago
Selected Answer: C
Why not C?
upvoted 1 times
Dken
4 months, 2 weeks ago
You can created collect, and distribute in a timely and appropriate manner that does not mean you are complying with the Communication Plan, just that the communications sent are correct.
upvoted 1 times
...
...
garlicbread
1 year, 4 months ago
why isn't it A?
upvoted 2 times
...
ChymKuBoy
1 year, 5 months ago
Selected Answer: B
B for sure
upvoted 2 times
...
ale1231
3 years, 3 months ago
B. Ensures that the information needs of the project and the stakeholders are met
upvoted 2 times
...
MoonManBlue
4 years, 1 month ago
B-Ensures the information needs of the stakeholders are met-10.3
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago