Why the other options are incorrect or incomplete:
A. Procurement documents and contracts are relevant for cost control and procurement management, but not primary documents for determining the full project budget.
C. Business case and project charter are initiating phase documents — they provide high-level financial info but not the detailed data needed for budgeting.
D. Scope baseline and activity list are important in cost estimation, but do not directly determine the budget without cost-related data like estimates or risk factors.
The correct option is B. Basis of estimates, cost estimates, project schedule, and risk register can help to determine the budget for the project.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MoonManBlue
Highly Voted 3 years, 3 months agoJesseChou_123
Most Recent 6 days, 6 hours agoChymKuBoy
7 months, 3 weeks agoIbrahim_M
8 months, 3 weeks ago