exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 36 discussion

Actual exam question from PMI's CAPM
Question #: 36
Topic #: 1
[All CAPM Questions]

Which project documents can determine the budget?

  • A. Procurement documents, contracts, requirements documentation, and basis of estimates
  • B. Basis of estimates, cost estimates, project schedule, and risk register
  • C. Business case, project charter, statement of work, and cost estimates
  • D. Scope baseline, resource management plan, activity list, and assumption log
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 3 months ago
B-Basis of Estimates, Cost Estimates, Project Schedule, Risk Register-7.3
upvoted 5 times
...
JesseChou_123
Most Recent 6 days, 6 hours ago
Selected Answer: B
Why the other options are incorrect or incomplete: A. Procurement documents and contracts are relevant for cost control and procurement management, but not primary documents for determining the full project budget. C. Business case and project charter are initiating phase documents — they provide high-level financial info but not the detailed data needed for budgeting. D. Scope baseline and activity list are important in cost estimation, but do not directly determine the budget without cost-related data like estimates or risk factors.
upvoted 1 times
...
ChymKuBoy
7 months, 3 weeks ago
Selected Answer: B
B for sure
upvoted 1 times
...
Ibrahim_M
8 months, 3 weeks ago
Selected Answer: B
The correct option is B. Basis of estimates, cost estimates, project schedule, and risk register can help to determine the budget for the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...