exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 36 discussion

Actual exam question from PMI's CAPM
Question #: 36
Topic #: 1
[All CAPM Questions]

Which project documents can determine the budget?

  • A. Procurement documents, contracts, requirements documentation, and basis of estimates
  • B. Basis of estimates, cost estimates, project schedule, and risk register
  • C. Business case, project charter, statement of work, and cost estimates
  • D. Scope baseline, resource management plan, activity list, and assumption log
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 1 month ago
B-Basis of Estimates, Cost Estimates, Project Schedule, Risk Register-7.3
upvoted 5 times
...
ChymKuBoy
Most Recent 5 months, 4 weeks ago
Selected Answer: B
B for sure
upvoted 1 times
...
Ibrahim_M
6 months, 3 weeks ago
Selected Answer: B
The correct option is B. Basis of estimates, cost estimates, project schedule, and risk register can help to determine the budget for the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago