To which knowledge area does the Collect Requirements process belong?

  • A. Quality Management
  • B. Scope Management
  • C. Cost Management
  • D. Integration Management
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
101bethie101
4 months, 2 weeks ago
Selected Answer: B
You gotta collect requirements to create the scope
upvoted 1 times
...
theplaceholder
9 months ago
Selected Answer: B
correct
upvoted 1 times
...
MoonManBlue
3 years, 7 months ago
B-Scope Management-Chapter 5
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago