What communication methods would a project manager use for overall effective project communication?

  • A. Interactive communication, push communication, interpersonal communication
  • B. Interactive communication, push communication, pull communication
  • C. Push communication, pull communication, interpersonal communication
  • D. Pull communication, interactive communication, interpersonal communication
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 day, 18 hours ago
Selected Answer: B
A, C, and D mention interpersonal communication, which is a style or technique, not a core communication method as categorized in the PMBOK Guide.
upvoted 1 times
...
041ba31
1 year ago
Selected Answer: B
B. Interactive communication, push communication, pull communication A project manager typically uses a combination of communication methods for overall effective project communication.
upvoted 1 times
...
anfacer
2 years ago
10.1.2.5 Communication methods. pg374
upvoted 2 times
...
MoonManBlue
4 years, 2 months ago
B-Interactive, push, and pull information
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...