Stakeholder identification and engagement should begin during what phrase of the project?

  • A. After the project management plan is completed
  • B. After the stakeholder engagement plan is completed
  • C. As soon as the project charter has been approved
  • D. After the communications management plan is completed
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
4 days, 19 hours ago
Selected Answer: C
Why the other options are incorrect: A. After the project management plan is completed ❌ Too late — stakeholder identification is necessary input for developing the project management plan. B. After the stakeholder engagement plan is completed ❌ Illogical — you must identify stakeholders first in order to create a stakeholder engagement plan. D. After the communications management plan is completed ❌ Also too late — stakeholder identification is a prerequisite for developing communication strategies.
upvoted 1 times
...
MoonManBlue
8 months, 3 weeks ago
C-As soon as the Project Charter has been approved
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...