exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 38 discussion

Actual exam question from PMI's PMI-ACP
Question #: 38
Topic #: 1
[All PMI-ACP Questions]

The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business.
What should the product owner have done differently?

  • A. Demonstrated only the completed stories and seek stakeholder feedback
  • B. Presented the budget situation and review the cost variance
  • C. Reviewed the test results to gain confidence from the stakeholders
  • D. Presented a demo of all the stories including the work in progress stories
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
HTTPS
Highly Voted 3 years, 6 months ago
A - Correct From The Scrum Guide: “If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.”
upvoted 6 times
...
Nervys
Most Recent 11 months ago
Selected Answer: A
A for sure
upvoted 1 times
...
Troplev
1 year, 7 months ago
Selected Answer: A
Vote A
upvoted 1 times
...
Minhha3
1 year, 7 months ago
Vote A
upvoted 1 times
...
Petrevski
1 year, 8 months ago
Selected Answer: A
A - correct
upvoted 1 times
...
Smokeyofficiial
1 year, 8 months ago
Option A. Demonstrated only the completed stories and seek stakeholder feedback. This aligns with the Agile principle of "Working software over comprehensive documentation" and the Agile practice of "Continuous feedback and adaptation." By demonstrating only the completed stories, the product owner can show tangible progress and gain stakeholder feedback on the work completed. This approach enables the team to prioritize feedback and make any necessary adjustments early in the development process, rather than waiting until the end of the project to assess stakeholder satisfaction. Additionally, demonstrating only completed stories helps the team to focus on delivering high-quality, working software, which is the primary goal of Agile development.
upvoted 2 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: A
Going with A.
upvoted 1 times
...
7029
1 year, 10 months ago
Selected Answer: A
A is most
upvoted 1 times
...
richck102
2 years, 4 months ago
i vote A
upvoted 1 times
...
tpkhoa
3 years, 2 months ago
For me, the answer is B. It mentioned in scrumguide 2017 :Review of the timeline, budget, potential capabilities, and marketplace for the next anticipated releases of functionality or capability of the product. https://scrumguides.org/docs/scrumguide/v2017/2017-Scrum-Guide-US.pdf
upvoted 1 times
...
pandat
3 years, 5 months ago
Product Owner can explains what has been done and what have not been done. However, the Demo should only cover the "Done". so A.
upvoted 4 times
...
Sky_Chaser
3 years, 11 months ago
https://mozaicworks.com/blog/incomplete-stories-in-sprint-reviews/
upvoted 1 times
srv3
3 years, 11 months ago
Each completed story is demoed as part of a working, tested system—preferably in a staging environment that closely resembles the production environment. https://www.scaledagileframework.com/iteration-review/
upvoted 2 times
...
...
Orikto
4 years, 1 month ago
in the questions it already mentioned "a demo of all the stories to the business.? how come again dothe same thing ? Question asking what could be done differently ? Make sense ?
upvoted 1 times
...
navingthomas
4 years, 1 month ago
From the statement "demo of all the stories to the business", it is clear uncompleted stories were also included for demo. The question is to know what PO should have done differently? In this context, I believe Option A is the correct choice.
upvoted 1 times
...
praveenkumard23
4 years, 2 months ago
Answer should be A .. only working stories will be demonstrated
upvoted 3 times
xero180sx
4 years, 2 months ago
You can demo incomplete stories to obtain feedback if there is enough functionality. We're not restricted to only complete stories. Answer is D
upvoted 1 times
srv3
3 years, 11 months ago
No, team should not do it.
upvoted 3 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...