The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What should the product owner have done differently?
A.
Demonstrated only the completed stories and seek stakeholder feedback
B.
Presented the budget situation and review the cost variance
C.
Reviewed the test results to gain confidence from the stakeholders
D.
Presented a demo of all the stories including the work in progress stories
A - Correct
From The Scrum Guide:
“If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.”
Option A.
Demonstrated only the completed stories and seek stakeholder feedback. This aligns with the Agile principle of "Working software over comprehensive documentation" and the Agile practice of "Continuous feedback and adaptation." By demonstrating only the completed stories, the product owner can show tangible progress and gain stakeholder feedback on the work completed. This approach enables the team to prioritize feedback and make any necessary adjustments early in the development process, rather than waiting until the end of the project to assess stakeholder satisfaction. Additionally, demonstrating only completed stories helps the team to focus on delivering high-quality, working software, which is the primary goal of Agile development.
For me, the answer is B.
It mentioned in scrumguide 2017 :Review of the timeline, budget, potential capabilities, and marketplace for the next
anticipated releases of functionality or capability of the product.
https://scrumguides.org/docs/scrumguide/v2017/2017-Scrum-Guide-US.pdf
Each completed story is demoed as part of a working, tested system—preferably in a staging environment that closely resembles the production environment.
https://www.scaledagileframework.com/iteration-review/
in the questions it already mentioned "a demo of all the stories to the business.? how come again dothe same thing ? Question asking what could be done differently ? Make sense ?
From the statement "demo of all the stories to the business", it is clear uncompleted stories were also included for demo. The question is to know what PO should have done differently? In this context, I believe Option A is the correct choice.
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
HTTPS
Highly Voted 3 years, 6 months agoNervys
Most Recent 11 months agoTroplev
1 year, 7 months agoMinhha3
1 year, 7 months agoPetrevski
1 year, 8 months agoSmokeyofficiial
1 year, 8 months agoInvisibleBeing
1 year, 10 months ago7029
1 year, 10 months agorichck102
2 years, 4 months agotpkhoa
3 years, 2 months agopandat
3 years, 5 months agoSky_Chaser
3 years, 11 months agosrv3
3 years, 11 months agoOrikto
4 years, 1 month agonavingthomas
4 years, 1 month agopraveenkumard23
4 years, 2 months agoxero180sx
4 years, 2 months agosrv3
3 years, 11 months ago