A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?

  • A. Schedule regular meetings with the scrum team to write, groom, and size user stories
  • B. Focus on stores based on the highest number of story points to first address those items with the highest value
  • C. Seek regular input from project stakeholders, and reflect this input in the backlog's priorities
  • D. Schedule in-person, monthly meetings with key stakeholders to review the project's progress
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
srv3
Highly Voted 2 years, 11 months ago
B and D are both incorrect. A and C both correct, but if P.O. can choose only one of that activities, then C is much more useful for the project success. C is the best answer
upvoted 6 times
...
tsangckl
Highly Voted 3 years, 1 month ago
SM do the meetings, and it can regular do at split planning in each split. C is the answer.
upvoted 5 times
...
Petrevski
Most Recent 6 months, 4 weeks ago
Selected Answer: C
C = correct. That's the first step!
upvoted 1 times
...
Minhha3
7 months, 2 weeks ago
Vote C
upvoted 1 times
...
InvisibleBeing
10 months ago
Selected Answer: C
I believe C is correct due to the wordings: "fast-moving project".
upvoted 1 times
...
richck102
1 year, 4 months ago
C sure
upvoted 1 times
...
JackNguyenvn
1 year, 7 months ago
C is correct
upvoted 2 times
...
Admirable
2 years, 4 months ago
C is the best answer.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.