exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 20 discussion

Actual exam question from PMI's PMI-ACP
Question #: 20
Topic #: 1
[All PMI-ACP Questions]

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

  • A. Collect stakeholder requirements
  • B. Conduct an iteration planning meeting
  • C. Communicate product backlog items to the stakeholders
  • D. Facilitate a product development roadmap workshop
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
Highly Voted 3 years, 6 months ago
D Roadmap is a means to communicate with both internal & external stakeholders
upvoted 7 times
...
tsangckl
Highly Voted 3 years, 7 months ago
D, face to face communication.
upvoted 5 times
...
hyanesimo
Most Recent 6 months, 1 week ago
it is A
upvoted 1 times
...
Imrangoshi
8 months, 3 weeks ago
Selected Answer: D
D is the Correct Answer
upvoted 1 times
...
Raksim
1 year, 1 month ago
To ensure that all key stakeholders are properly engaged in planning, an agile practitioner can facilitate a product development roadmap workshop. This workshop is an opportunity to bring together all relevant stakeholders to collaborate and prioritize product features, establish goals, and create a high-level plan for delivering those features. It is a chance for stakeholders to share their perspectives and ensure that everyone is aligned on the product vision and objectives. The workshop helps to ensure that all stakeholders have a voice and are involved in the planning process, leading to a more collaborative and effective approach to product development.\
upvoted 3 times
...
cutri89
1 year, 2 months ago
Selected Answer: B
i thik this
upvoted 1 times
...
Petrevski
1 year, 2 months ago
Selected Answer: D
D - correct. A - PO is communicating with the stakeholders, related to their requirements
upvoted 1 times
Petrevski
1 year, 2 months ago
B - stakeholders do not take part in planning, the team do. C - similar to A.
upvoted 1 times
...
...
InvisibleBeing
1 year, 4 months ago
Selected Answer: D
D sounds better.
upvoted 1 times
...
7029
1 year, 4 months ago
Selected Answer: D
D is the most
upvoted 1 times
...
cozyhead
1 year, 9 months ago
D here
upvoted 1 times
...
richck102
1 year, 10 months ago
D sure
upvoted 1 times
...
JackNguyenvn
2 years, 2 months ago
I think D is correct
upvoted 2 times
...
GPena
3 years, 7 months ago
D is better
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel