Suggested Answer:ACD🗳️
The outputs to the determine budget process are as follows: Cost performance baseline: The cost performance baseline is an authorized time-phased budget at completion. Project funding requirements: The project funding requirements are determined from total funding requirements and periodic funding requirements. Project document updates: The project document updates consists of risk register, cost estimates and project schedule. Incorrect Answers: B: Scope baseline is an input to the determine budget process.
out of Cost Budget is only Cost baseline and Project Funding Requirements
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMI-SP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tauseefnaz
7 months ago