exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 79 discussion

Actual exam question from PMI's PMI-ACP
Question #: 79
Topic #: 1
[All PMI-ACP Questions]

A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.
What should the Scrum Master do?

  • A. Point out that the team chose to work on other requirements to speed up the project
  • B. Ensure that the product owner reviews the contents of the information radiator
  • C. Ensure that the next sprint planning meeting reviews the satisfaction histogram
  • D. Point out that it is the responsibility of the product owner to clarify requirements
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
srv3
Highly Voted 3 years ago
Question is: "The product owner wants to know why the status of these requirements was not communicated." There is no question why priorities were not taken into consideration when sprint backlog formed. So B is correct answer.
upvoted 10 times
...
Admirable
Highly Voted 2 years, 3 months ago
B is the best answer. The team communicates status using the information radiator.
upvoted 7 times
...
Petrevski
Most Recent 7 months, 3 weeks ago
Selected Answer: B
B = correct
upvoted 1 times
...
Minhha3
8 months ago
Vote B
upvoted 1 times
...
Smokeyofficiial
8 months, 2 weeks ago
Option B. In Agile Framework, an information radiator is a visible display that shows the project's progress, including the status of user stories and requirements. The Scrum Master is responsible for ensuring that stakeholders, including the product owner, have access to the information radiator and understand its contents. In this scenario, the Scrum Master should ensure that the product owner reviews the contents of the information radiator to gain a clear understanding of the status of the requirements.
upvoted 1 times
...
InvisibleBeing
10 months, 2 weeks ago
Selected Answer: B
B is correct.
upvoted 1 times
InvisibleBeing
10 months, 2 weeks ago
The reason: The question is not about clarifying requirements or prioritization. The question is about why the status of the requirements not communicated to the PO. Transparency is achieved with the help of information radiators, so the scrum master needs to ensure that PO has access to the information radiators.
upvoted 1 times
...
...
cozyhead
1 year, 3 months ago
Selected Answer: B
BS is the best answer in this case
upvoted 1 times
cozyhead
1 year, 3 months ago
B* sorry
upvoted 1 times
...
...
richck102
1 year, 4 months ago
i vote B
upvoted 1 times
...
JackNguyenvn
1 year, 8 months ago
The answer is B
upvoted 2 times
...
Abbey2
2 years, 4 months ago
When you are commenting, please state your preferred answer first, then write to support your option or reasons why you believe other options are wrong. Reference(s) to your answer are also encouraged.
upvoted 2 times
...
Athena75
2 years, 8 months ago
The PO nd the Dev Team work together on the requirements in the iteration. PO must approve on the work the Dev Team is working on. If that is not included it links to the PO. So these requirements must be approved by the PO. I think D is the answer.
upvoted 1 times
...
snow5
3 years ago
Agile Principle #4: "Business people and developers must work together daily throughout the project.". Accordingly, PO should be communicated through info radiator
upvoted 6 times
...
snow5
3 years ago
The question is about the communication matter not the role of PO, I think B is the right answer
upvoted 5 times
...
snow5
3 years ago
Why not B ?
upvoted 2 times
...
GPena
3 years, 1 month ago
D is the answer and it is PO responsibility to ensure that the DT working on it
upvoted 1 times
GPena
2 years, 10 months ago
Moving to the right answer. B
upvoted 4 times
...
...
Mokel
3 years, 1 month ago
That seems wrong to me. To me (D) seems much more appropriate.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...