A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated. What should the Scrum Master do?
A.
Point out that the team chose to work on other requirements to speed up the project
B.
Ensure that the product owner reviews the contents of the information radiator
C.
Ensure that the next sprint planning meeting reviews the satisfaction histogram
D.
Point out that it is the responsibility of the product owner to clarify requirements
Question is: "The product owner wants to know why the status of these requirements was not communicated."
There is no question why priorities were not taken into consideration when sprint backlog formed.
So B is correct answer.
Option B.
In Agile Framework, an information radiator is a visible display that shows the project's progress, including the status of user stories and requirements. The Scrum Master is responsible for ensuring that stakeholders, including the product owner, have access to the information radiator and understand its contents. In this scenario, the Scrum Master should ensure that the product owner reviews the contents of the information radiator to gain a clear understanding of the status of the requirements.
The reason:
The question is not about clarifying requirements or prioritization. The question is about why the status of the requirements not communicated to the PO. Transparency is achieved with the help of information radiators, so the scrum master needs to ensure that PO has access to the information radiators.
When you are commenting, please state your preferred answer first, then write to support your option or reasons why you believe other options are wrong. Reference(s) to your answer are also encouraged.
The PO nd the Dev Team work together on the requirements in the iteration. PO must approve on the work the Dev Team is working on. If that is not included it links to the PO. So these requirements must be approved by the PO. I think D is the answer.
Agile Principle #4:
"Business people and developers must work together daily throughout the project.". Accordingly, PO should be communicated through info radiator
That seems wrong to me.
To me (D) seems much more appropriate.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
srv3
Highly Voted 3 years agoAdmirable
Highly Voted 2 years, 3 months agoPetrevski
Most Recent 7 months, 3 weeks agoMinhha3
8 months agoSmokeyofficiial
8 months, 2 weeks agoInvisibleBeing
10 months, 2 weeks agoInvisibleBeing
10 months, 2 weeks agocozyhead
1 year, 3 months agocozyhead
1 year, 3 months agorichck102
1 year, 4 months agoJackNguyenvn
1 year, 8 months agoAbbey2
2 years, 4 months agoAthena75
2 years, 8 months agosnow5
3 years agosnow5
3 years agosnow5
3 years agoGPena
3 years, 1 month agoGPena
2 years, 10 months agoMokel
3 years, 1 month ago