I think 'D', as the technical problem has been reported after collaborative team work and appears to be an escalation at this point. the SM could see this as impediment and bring in necessary help.
It's not stated in the question that the problem was reported after collaborative team work. Team working together on problem resolution is very agile approach and that's the keyword here. Option C then.
Team should always collaboratively work out on stories/technical issues. Now if there is a bottleneck/impediment which may impact delivery, then it needs to be expedited. So D looks good.
“Asking” in option C sounds like a command and control style which is not a way of agile. Hence engaging a technical manager to solve a technical problem is a good approach. D is my choice.
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mokel
Highly Voted 4 years agoNervys
Most Recent 10 months, 1 week agoImrangoshi
1 year, 1 month agoAgile_Dario_Conde
1 year, 5 months agoBalaraju
1 year, 5 months agoImGonnaPassIt
7 months agocutri89
1 year, 7 months agoPetrevski
1 year, 7 months agoInvisibleBeing
1 year, 9 months agoLuanND
1 year, 9 months ago7029
1 year, 9 months agorichck102
2 years, 3 months agoJackNguyenvn
2 years, 7 months agoAlaaradwan
3 years, 3 months agoAzurance
3 years, 3 months agohadecrown
3 years, 6 months agoGPena
3 years, 12 months ago