A technical problem arises that will likely impact the stories planned for delivery in the current sprint.
What should the scrum master do?

  • A. Consider adding a story to the next sprint to seek resolution
  • B. Immediately solve the problem on behalf of the team
  • C. Ask the team to collaboratively work out a solution
  • D. Engage a technical manager to assist with finding a solution
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mokel
Highly Voted 4 years ago
Should be (C)
upvoted 11 times
...
Nervys
Most Recent 10 months, 1 week ago
C for sure
upvoted 1 times
...
Imrangoshi
1 year, 1 month ago
Selected Answer: C
C is the Correct Answer
upvoted 1 times
...
Agile_Dario_Conde
1 year, 5 months ago
Selected Answer: C
Collaborate
upvoted 2 times
...
Balaraju
1 year, 5 months ago
Selected Answer: D
I think 'D', as the technical problem has been reported after collaborative team work and appears to be an escalation at this point. the SM could see this as impediment and bring in necessary help.
upvoted 1 times
ImGonnaPassIt
7 months ago
It's not stated in the question that the problem was reported after collaborative team work. Team working together on problem resolution is very agile approach and that's the keyword here. Option C then.
upvoted 1 times
...
...
cutri89
1 year, 7 months ago
Selected Answer: D
i think this
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: C
C - correct
upvoted 1 times
...
InvisibleBeing
1 year, 9 months ago
Selected Answer: C
C is correct.
upvoted 1 times
...
LuanND
1 year, 9 months ago
Selected Answer: C
Should be (C)
upvoted 1 times
...
7029
1 year, 9 months ago
Selected Answer: C
C is the most
upvoted 1 times
...
richck102
2 years, 3 months ago
i vote C
upvoted 1 times
...
JackNguyenvn
2 years, 7 months ago
C is correct
upvoted 1 times
...
Alaaradwan
3 years, 3 months ago
c correct
upvoted 2 times
...
Azurance
3 years, 3 months ago
Team should always collaboratively work out on stories/technical issues. Now if there is a bottleneck/impediment which may impact delivery, then it needs to be expedited. So D looks good.
upvoted 1 times
...
hadecrown
3 years, 6 months ago
“Asking” in option C sounds like a command and control style which is not a way of agile. Hence engaging a technical manager to solve a technical problem is a good approach. D is my choice.
upvoted 2 times
...
GPena
3 years, 12 months ago
It must be C
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago