A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years.
What should the scrum master do first?

  • A. Work with the customers to build the product backlog and identify their initial requirements
  • B. Meet with the stakeholders and enterprise architects to understand the project's vision
  • C. Plan and execute a sprint 0 to establish the project's foundational needs
  • D. Create a backlog, and execute a sprint 1 to quickly deliver value to the customers
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Athena75
Highly Voted 3 years, 8 months ago
The answer is B Read the question again and review the answers carefully What is the FIRST thing the SM has to do on a project? Understand the vision, know the stakeholders Remember Sprint Panning and execution is not done by the SM only. This is done by the team. SM bridges the Dev. Team and the Stakeholders
upvoted 10 times
ITAgile
1 year ago
That sounds like the PO role. I think D is correctm if you take in consideration "deliver valaue"
upvoted 1 times
...
...
chlaithem
Most Recent 10 months, 2 weeks ago
Selected Answer: B
Understanding the bigger picture, Stakeholder alignment. C: Sprint 0 can be valuable for establishing technical frameworks and tools, but its effectiveness hinges on a clear understanding of the project's overall direction. D: Delivering value quickly is a noble goal, but doing so without alignment with the larger vision and stakeholder expectations might miss the mark or generate rework later.
upvoted 2 times
...
MattAnya
1 year ago
Selected Answer: B
This ensures that the scrum master is informed about the strategic importance of the project including the long term vision of the project
upvoted 1 times
...
Petrevski
1 year, 6 months ago
Selected Answer: B
B = correct. It is first of all! PS: the PO is building and managing the product backlog.
upvoted 3 times
Petrevski
1 year, 3 months ago
Have in mind: - According to the Scrum guide there's no Sprint 0! - SM doesn't plan - the team does! - The SM doesn't create backlog - the PO does!
upvoted 1 times
...
...
Minhha3
1 year, 7 months ago
Vote D
upvoted 1 times
Minhha3
1 year, 6 months ago
Change to C
upvoted 1 times
...
...
richck102
2 years, 4 months ago
i vote C
upvoted 2 times
...
JackNguyenvn
2 years, 7 months ago
I choose C
upvoted 1 times
...
Oshera
2 years, 11 months ago
It's C. He has already accepted the job, the overall vision has already been explained. Now he needs a breakdown of the vision and his team needs to understand what the stakeholders etc are looking for (foundational needs) which can be accomplished by iteration 0.
upvoted 1 times
...
RKarpe
3 years ago
Here the SC only assumes the project to be important and needs to be delivered in 3 years. There is no hurry to deliver any value. Unless the vision is understood, sprint cannot start. I go with B
upvoted 1 times
...
Admirable
3 years, 2 months ago
The best answer is C. Sprint 0 activities include the following: • Project visionaries and leaders • Scrum Team members • Agile Coach • Extended team members who provide support activities for establishing a team The Product vision, backlog, release plan, training etc is created during Sprint 0. https://pmi-svc.org/library/forums/agile/1306-sprint-0-activities-2018-12-05/file
upvoted 3 times
...
Azurance
3 years, 4 months ago
I WOULD PICK C.
upvoted 2 times
...
srv3
3 years, 11 months ago
A. Work with the customers to build the product backlog and identify their initial requirements. > P.O. should do this B. Meet with the stakeholders and enterprise architects to understand the project's vision. > S.M. can provide workshop tools to handle this meeting but Scrum Team should meet, not S.M. or P.O. only C. Plan and execute a sprint 0 to establish the project's foundational needs. > this is the best answer D. Create a backlog, and execute a sprint 1 to quickly deliver value to the customers. > P.O. should create backlog, not S.M.
upvoted 2 times
Ozmar
3 years ago
Execute Sprint 0 is not SM task, its Development Team, So it would be B
upvoted 1 times
...
...
snow5
3 years, 11 months ago
B cant be the right answer for one reason, bcz PO shares the project vision with the team. including SM
upvoted 3 times
...
snow5
4 years ago
C make sense ! What is sprint 0? Sprint zero usually takes place before the formal start of the project and/or at a team's inception. The goal of the Sprint is for the Development Team to come together to develop a minimal number of User Stories, project skeleton, story mapping, and develop a workable product. This Sprint should be kept lightweight and relatively high level. It is all about the origination of project exploration and gaining an understanding of where you want to head while keeping velocity low.
upvoted 2 times
Ozmar
3 years ago
Yes but it is implemented by Development Team not SM
upvoted 1 times
...
...
Wmahmoudi
4 years ago
For me, B is the answer
upvoted 2 times
...
GPena
4 years ago
I think the answer is B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...