exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 46 discussion

Actual exam question from PMI's PMI-ACP
Question #: 46
Topic #: 1
[All PMI-ACP Questions]

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered.
How should an agile practitioner work with the team to help identify the iteration's remaining scope?

  • A. Convince the team to stop planning and keep the size small
  • B. Identify the technically minimal and achievable tasks
  • C. Refer to the remaining prioritized backlog items
  • D. Select some of the smallest items from the backlog
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
Highly Voted 3 years ago
C is the correct answer, the backlog is the key reference for all stories.
upvoted 6 times
...
Minhha3
Most Recent 7 months, 2 weeks ago
Vote C
upvoted 1 times
...
Petrevski
8 months ago
Selected Answer: C
C = correct.
upvoted 1 times
...
InvisibleBeing
10 months, 1 week ago
Selected Answer: C
C is correct.
upvoted 1 times
...
richck102
1 year, 4 months ago
C sure
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...