Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.
What should the product owner do next?
Ntp
8 months, 2 weeks agoPetrevski
1 year, 1 month agoSmokeyofficiial
1 year, 1 month agoTompaL111
1 year, 2 months agoInvisibleBeing
1 year, 3 months agominwang
1 year, 8 months agocozyhead
1 year, 8 months agorichck102
1 year, 9 months agoNguyenAPT
2 years agoJackNguyenvn
2 years, 1 month agoAbbey2
2 years, 9 months agoAthena75
3 years, 1 month agosrv3
3 years, 5 months agosnow5
3 years, 5 months agosnow5
3 years, 5 months ago