Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.
What should the product owner do next?
Ntp
10 months, 1 week agoPetrevski
1 year, 3 months agoSmokeyofficiial
1 year, 3 months agoTompaL111
1 year, 4 months agoInvisibleBeing
1 year, 5 months agominwang
1 year, 9 months agocozyhead
1 year, 10 months agorichck102
1 year, 11 months agoNguyenAPT
2 years, 2 months agoJackNguyenvn
2 years, 3 months agoAbbey2
2 years, 11 months agoAthena75
3 years, 3 months agosrv3
3 years, 7 months agosnow5
3 years, 7 months agosnow5
3 years, 7 months ago