During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans. What should the agile practitioner do?
A.
Provide all information requested by the stakeholder
B.
Set expectations regarding the appropriate level of details requested during this stage
C.
Inform the stakeholder that no detailed documents are provided using agile practices
D.
Ask the team to supply the information to the stakeholder
Bcz some documents can be provided when required. Option C assumes that documents are never provided. Imagine that you are doing Medical/Life system with XP or Crystal Clear :)
So B seems to be correct answer.
upvoted 5 times
...
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Petrevski
7 months agoMinhha3
7 months, 2 weeks agoInvisibleBeing
10 months agorichck102
1 year, 4 months agosnow5
3 years agosrv3
2 years, 11 months ago