What is the purpose of mitigating negative risks as a part of the risk response process?

  • A. To transfer the probability of a risk happening to a third party, and to reduce the severity of the impact
  • B. To reduce the probability of a risk happening, and/or reduce the severity of the impact
  • C. To accept the probability of a risk happening to reduce the severity of the impact
  • D. To increase the probability of a risk happening, but reduce the severity of the impact
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PMP1
Highly Voted 3 years, 6 months ago
should be B
upvoted 7 times
...
Linkedin_Dario_Conde
Most Recent 6 months, 2 weeks ago
Selected Answer: B
B is correct because reducing is the same as mitigating the issue.
upvoted 1 times
...
aws_guru1
1 year, 3 months ago
Selected Answer: B
B Mitigating = reducing the probability
upvoted 1 times
...
ahmedSayis
2 years, 6 months ago
Mitigating = reducing the probability
upvoted 1 times
...
lucksuman
2 years, 7 months ago
Mitigating = reducing the probability
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...