A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve.
From which of the following sources should the funds be drawn to cover the risk mitigation?
Linkedin_Dario_Conde
6 months agoAzharmak
6 months agoaws_guru1
1 year, 2 months agogen2ty
2 years, 10 months agocskhal
3 years, 5 months ago