An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses. What can happen as a result?
A.
The team will be unable to understand the iteration's status
B.
The team will be unable to judge the project design's validity
C.
The team cannot give accurate updates to management
D.
Team collaboration cannot be measured effectively
Not sure A or C. In my opinion, A is more likely to be correct because of the slow entry of story statuses, first the team will be unable to understand the iteration's status, and after that comes C - the team couldn't give accurate updates to management.
The confusing thing is:
A - the team has daily meetings and this issue can be shared, maybe this issue happened at the end of the iteration
D - the team does not give updates to management, maybe this refers to reviews
Anyway, A comes first, then D.
Option C.
In Agile Framework, team velocity is a measure of how much work a team can complete in a given iteration, and it is an essential metric for predicting project timelines and delivering value. If one team member is slow to enter story statuses, it can impact the accuracy of the team's velocity, which can make it challenging to provide accurate updates to management. Therefore, Option C is the correct answer.
Options A, B, and D are not accurate because a single team member's behavior is unlikely to have such a significant impact on the team's ability to understand iteration status, judge the project design's validity, or measure team collaboration effectively. However, if the slow entry of story statuses persists, it can lead to other issues, such as difficulty in identifying blockers, delays in resolving dependencies, and misaligned expectations within the team, which can ultimately affect project success.
A looks correct. Not sure if Agile team provide updates to management. The roadmap and KPI will have incorrect data, which will show an incorrect iteration status.
C is correct but A goes before it. Team can't give updates (via information radiator or other vay) because them don't understand iteration status also.
upvoted 2 times
...
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TonyMac
7 months agoPetrevski
1 year agoPetrevski
1 year agoMinhha3
1 year agoSmokeyofficiial
1 year, 1 month agoInvisibleBeing
1 year, 3 months agorichck102
1 year, 9 months agoJackNguyenvn
2 years, 1 month agoAbbey2
2 years, 9 months agoAzurance
2 years, 9 months agoHTTPS
2 years, 11 months agoHaiHN
3 years, 4 months agosrv3
3 years, 4 months ago