Question #: 78
Topic #: 1
[All PMI-ACP Questions]

An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.
What can happen as a result?

  • A. The team will be unable to understand the iteration's status
  • B. The team will be unable to judge the project design's validity
  • C. The team cannot give accurate updates to management
  • D. Team collaboration cannot be measured effectively
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TonyMac
7 months ago
Selected Answer: A
The product owner provides updates to management, not the team.
upvoted 1 times
...
Petrevski
1 year ago
Selected Answer: A
Not sure A or C. In my opinion, A is more likely to be correct because of the slow entry of story statuses, first the team will be unable to understand the iteration's status, and after that comes C - the team couldn't give accurate updates to management. The confusing thing is: A - the team has daily meetings and this issue can be shared, maybe this issue happened at the end of the iteration D - the team does not give updates to management, maybe this refers to reviews Anyway, A comes first, then D.
upvoted 1 times
Petrevski
1 year ago
D = C :)
upvoted 1 times
...
...
Minhha3
1 year ago
Vote A
upvoted 1 times
...
Smokeyofficiial
1 year, 1 month ago
Option C. In Agile Framework, team velocity is a measure of how much work a team can complete in a given iteration, and it is an essential metric for predicting project timelines and delivering value. If one team member is slow to enter story statuses, it can impact the accuracy of the team's velocity, which can make it challenging to provide accurate updates to management. Therefore, Option C is the correct answer. Options A, B, and D are not accurate because a single team member's behavior is unlikely to have such a significant impact on the team's ability to understand iteration status, judge the project design's validity, or measure team collaboration effectively. However, if the slow entry of story statuses persists, it can lead to other issues, such as difficulty in identifying blockers, delays in resolving dependencies, and misaligned expectations within the team, which can ultimately affect project success.
upvoted 2 times
...
InvisibleBeing
1 year, 3 months ago
Selected Answer: A
A is correct.
upvoted 1 times
...
richck102
1 year, 9 months ago
A sure
upvoted 1 times
...
JackNguyenvn
2 years, 1 month ago
A is correct
upvoted 2 times
...
Abbey2
2 years, 9 months ago
What is the purpose of daily scrum meeting. is it to provide updates to the management on daily basis? No! The answer should be A.
upvoted 2 times
...
Azurance
2 years, 9 months ago
A looks correct. Not sure if Agile team provide updates to management. The roadmap and KPI will have incorrect data, which will show an incorrect iteration status.
upvoted 2 times
...
HTTPS
2 years, 11 months ago
I would go for A.
upvoted 1 times
...
HaiHN
3 years, 4 months ago
Correcr answer should be C. A is not appropriate as the team has daily scrum to share their work status already.
upvoted 1 times
srv3
3 years, 4 months ago
C is correct but A goes before it. Team can't give updates (via information radiator or other vay) because them don't understand iteration status also.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago