Exam PMI-ACP topic 1 question 90 discussion

Actual exam question from PMI's PMI-ACP
Question #: 90
Topic #: 1
[All PMI-ACP Questions]

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work and to rely on outside specialists is impacting team velocity.
What should the agile team lead do?

  • A. Send the member to training
  • B. Ask the outside specialists if database administration is required from the team
  • C. Send one member to training only after asking the team if there is an issue with the current work flow
  • D. Wait until all members of the team can attend training
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
hadecrown
Highly Voted 2 years, 11 months ago
C also makes sense, because a decision cannot be made with suggestion of just one team member. Consensus is needed from other team members which makes C another viable option. For me I will go for C.
upvoted 5 times
...
Michaela0015
Most Recent 2 months, 2 weeks ago
Selected Answer: C
I would go with C: Send one member to training only after asking the team if there is an issue with the current workflow In an agile environment, it's important to consider the impact on the team as a whole. While individual skill development is valuable, decisions should be made collaboratively with the team.
upvoted 1 times
...
Akhundzada
7 months ago
Selected Answer: C
The agile team lead should choose option C. They should first discuss the concern with the entire team to understand if there's an issue with the current workflow due to the reliance on outside specialists. If the team collectively agrees that there's a challenge, then sending the concerned team member for database administrator training could be considered. This approach promotes collaboration and ensures that decisions are made collectively, aligning with Agile principles.
upvoted 1 times
...
hankun
7 months ago
A make sense. Because the question refer to agile team lead then he knew issue and no need to ask the team.
upvoted 1 times
...
Petrevski
11 months, 1 week ago
Selected Answer: A
A = correct. The team is self-organized. The team is accountable, not a certain member. T
upvoted 1 times
Petrevski
6 months, 1 week ago
Change to C
upvoted 1 times
...
...
Minhha3
11 months, 3 weeks ago
Vote A
upvoted 1 times
...
Smokeyofficiial
1 year ago
Option C. In Agile Framework, it's important to promote self-organizing and cross-functional teams, and to encourage team members to take on new responsibilities and develop new skills. However, it's also important to balance this with the need to maintain a sustainable pace of work and ensure that team members are not overburdened with work they are not qualified to do. In this scenario, the team lead should first ask the team if there is an issue with the current work flow and if the team member's inability to handle database administration is impacting velocity. If the team agrees that this is an issue, then sending the team member to training could be a good option. However, it's important to make sure that this training does not disrupt the team's ability to deliver on their current commitments, so sending only one member to training would be a more prudent approach.
upvoted 2 times
current_1903
11 months, 3 weeks ago
hi do you generally write these comment with your own? or just copy and paste? I ve seen your explanation and they are very well structured. If it is copy and paste, I wonder where you provide. Thank you.
upvoted 1 times
...
...
InvisibleBeing
1 year, 2 months ago
Selected Answer: C
I am going with C
upvoted 1 times
...
GrandMasta
1 year, 6 months ago
A is correct. A member of the team is unable to perform the job at hand. He is asking for training. If a member needs training to perform better, then to training he/she should go.
upvoted 1 times
...
richck102
1 year, 8 months ago
i vote C
upvoted 1 times
...
JackNguyenvn
1 year, 12 months ago
I choose C
upvoted 1 times
...
Abbey2
2 years, 8 months ago
As a SM, would you release a member for training even though it will affect the current work flow. The best answer is C
upvoted 3 times
...
Alaaradwan
2 years, 8 months ago
correct A
upvoted 1 times
...
Azurance
2 years, 8 months ago
A is my answer. C doesn't look correct, why the team lead would ask team if there is an issue with the current flow. A team lead is self emergent and should already know that.
upvoted 1 times
...
HTTPS
2 years, 10 months ago
A - Correct From PMI’s Agile Practice Guide, Page 41: “Cross-functional teams are critical because they can deliver finished work in the shortest possible time, with higher quality, without external dependencies.”
upvoted 1 times
...
GPena
3 years, 2 months ago
I think a training is good but after validation with the team. C is the my choice.
upvoted 4 times
GPena
3 years, 2 months ago
I change my choice to A. validation is not agile
upvoted 1 times
...
PMP1
3 years, 2 months ago
team member has said rely on outside specialists is not a solution, so A is answer
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...