exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 1 question 89 discussion

Actual exam question from PMI's PMI-SP
Question #: 89
Topic #: 1
[All PMI-SP Questions]

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

  • A. $176,675
  • B. $122,845
  • C. -$85,000
  • D. -$51,000
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
There is positive variance of $122,845 on Fred's project. Variances can be either positive or negative. Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule.
A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.
Incorrect Answers:
A: This is not a valid answer for the project.
C: This is the project's variance at completion.
D: This is the cost variance for the project.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
aleemulislam
3 years, 7 months ago
EV=0.6*2456900=1474140, PV=0.55*2456900, SV=EV-PV = 1474140-1351295=122845(+ve)
upvoted 2 times
...
CDKA
3 years, 10 months ago
EV = 2456900*0.65 = 1596985 PV = 2456900 * 0.6 = 1474140 Therefore, SV = EV - PV = 122845 (+ve ahead of schedule)
upvoted 3 times
...
Mopar
4 years, 8 months ago
Shouldn't the answer be: $1,525,140 - ($2,456,900 * .55(since it is 5% more complete than PLANNED) = $173,845?
upvoted 1 times
segunkay
9 months ago
When dealing SV, your actual cost doest not play any role. just dealing with EV and PV. AC inot in the equation.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago