Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
Location Chicago IL, USA

Exam PMI-ACP topic 1 question 664 discussion

Actual exam question from PMI's PMI-ACP
Question #: 664
Topic #: 1
[All PMI-ACP Questions]

What should the agile practitioner know about tracking velocity?

  • A. A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
  • B. A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
  • C. A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
  • D. A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
Show Suggested Answer Hide Answer

Suggested Answer: C

Comments

SILLYACP
3 weeks, 6 days ago
why not A?
upvoted 1 times
...
GPena
3 months, 4 weeks ago
I think B is the answer
upvoted 1 times
...

SaveCancel