Exam PMI-RMP topic 1 question 109 discussion

Actual exam question from PMI's PMI-RMP
Question #: 109
Topic #: 1
[All PMI-RMP Questions]

Which of the following represents the best description of the role of project manager for project risk management?

  • A. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management, assessing the impact of proposed scope changes
  • B. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the project management plan, participating in all aspects of the project risk management process
  • C. Approving the risk management plan, participating in all aspects of the project risk management process, auditing the risk management processes in the project
  • D. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management plan, participating in all aspects of the project risk management process
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ahmedSayis
6 months, 2 weeks ago
D. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management plan, participating in all aspects of the project risk management process
upvoted 1 times
...
gen2ty
10 months, 2 weeks ago
The key word is the PM role referenced to RM, D is the right answer in this context.
upvoted 1 times
...
hossam83
1 year, 4 months ago
D is the best answer
upvoted 1 times
...
edusousa
1 year, 4 months ago
Does PM approve the Project Management Plan?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...