exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 122 discussion

Actual exam question from PMI's PMI-RMP
Question #: 122
Topic #: 1
[All PMI-RMP Questions]

PESTLE, TECOP, and SPECTRUM are three examples of prompt lists that can be used during risk management activities. Prompt lists are used to do which of the following?

  • A. Simulate risk identification.
  • B. Perform a simulation with all prompted risks varying simultaneously.
  • C. Identify basic causes of risks of more fundamental forces.
  • D. Achieve the relative weighting of the risks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
Its T & T of Risk identification so answer is A.
upvoted 1 times
...
edusousa
4 years ago
"STimulate risk identification" not "Simulate risk identification."
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel