Question #: 27
Topic #: 1
[All PMI-RMP Questions]

The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one- month delay.
What should the project manager do next to reduce further delay?

  • A. Initiate a scope change request.
  • B. Schedule a project kick-off meeting.
  • C. Schedule a stakeholder meeting.
  • D. Engage the project sponsor/portfolio manager.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
_MCV_
1 year, 1 month ago
Selected Answer: C
For me, the best selected answer would be C
upvoted 1 times
...
Linkedin_Dario_Conde
1 year, 2 months ago
Selected Answer: C
C is the answer to solve the problem
upvoted 1 times
...
Aderike
1 year, 3 months ago
I would go with C
upvoted 1 times
...
OMG4567
1 year, 4 months ago
Selected Answer: C
I would invite for stakeholder meeting since all other options don't help to resolve the conflict.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...