Question #: 94
Topic #: 1
[All PMI-RMP Questions]

A six-month, USS1.2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones.
Based on this project data, what technique should the risk manager recommend to improve the risk management process?

  • A. Increase the risk manager's position to a full-time position and acquire a dedicated project schedule lead.
  • B. Adjust project risk thresholds to increase the number of residual risks on the project.
  • C. Increase the frequency of risk status meetings and update the risk management plan.
  • D. Perform a variance analysis and potentially allocate more reserves to improve risk mitigation.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheAWSGuru
10 months ago
Selected Answer: C
C is the right answer
upvoted 1 times
...
Azharmak
1 year, 5 months ago
How can Ans. be D? Already the available reserves have not been consumed so you don't need more reserves. Ans should be C
upvoted 1 times
...
Linkedin_Dario_Conde
1 year, 5 months ago
Selected Answer: C
Frequency of meetings will improve the process
upvoted 1 times
...
OMG4567
1 year, 7 months ago
Selected Answer: C
There is no evidence that increased reserves will help since its mentioned that most of the reserves are not spent. Also performing a variance analysis doesn't help the process. The solution with the future in mind is C - Increasing the frequency of meetings will help to improve the process.
upvoted 1 times
...
hossam83
4 years, 3 months ago
D is the best answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago