exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 72 discussion

Actual exam question from PMI's PMI-RMP
Question #: 72
Topic #: 1
[All PMI-RMP Questions]

Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed.
What recommendation could be implemented to prevent this from recurring?

  • A. Use the Monte Carlo simulation.
  • B. Implement a reserve analysis process.
  • C. Conduct more frequent reserve watch list status meetings.
  • D. Increase the contingency reserve.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
aws_guru1
7 months ago
Selected Answer: B
B is correct.
upvoted 1 times
...
hossam83
2 years, 9 months ago
B is the best answer
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago