Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed. What recommendation could be implemented to prevent this from recurring?
A.
Use the Monte Carlo simulation.
B.
Implement a reserve analysis process.
C.
Conduct more frequent reserve watch list status meetings.