Exam PMI-RMP topic 1 question 50 discussion

Actual exam question from PMI's PMI-RMP
Question #: 50
Topic #: 1
[All PMI-RMP Questions]

What identification technique is used to help reduce the ambiguity of a risk statement?

  • A. Driver, risk, outcome
  • B. Exploit, risk, accept
  • C. Probability, risk, impact
  • D. Cause, risk, effect
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
D. Risk metalanguage provides a three-part structured- cause, risk, and effect.
upvoted 1 times
...
RoyalWarrior
1 year, 10 months ago
Correct Answer is D. Risk metalanguage provides a three-part structured description of a risk that includes cause, risk, and effect.
upvoted 1 times
...
ahmedSayis
3 years, 2 months ago
D. Cause, risk, effect
upvoted 2 times
...
gen2ty
3 years, 6 months ago
D is the right answer. Risk are meant to be described in Cause-Risk-Effect format to remove ambiguity
upvoted 2 times
...
hossam83
4 years ago
D is the right because you talk about identification of risks not analysis so risk meta language( risk, effect ,cause) is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...