A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance.
Which aspect of risk impact is most important when designing the risk impact scale?

  • A. Technical performance
  • B. Cost
  • C. Technical requirements
  • D. Schedule
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snilu
11 months ago
.... but should not be done at the expense of performance. Technical performance is the correct answer.
upvoted 2 times
...
edusousa
1 year, 9 months ago
"This project is not technically complex, but has rigorous implementation timelines" Schedule is important (D)
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...