exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 162 discussion

Actual exam question from PMI's PMI-RMP
Question #: 162
Topic #: 1
[All PMI-RMP Questions]

A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are financial risks.
What procedure could the project manager use to identify other potential topics such as technical, quality, performance, project management, internal and external risks?

  • A. Review enterprise environmental factors.
  • B. Perform Monte Carlo analysis and Delphi technique.
  • C. Perform decision tree analysis and create an Ishikawa diagram.
  • D. Use existing prompt lists and risk breakdown structure.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
aws_guru1
8 months ago
Selected Answer: D
D. Use existing prompt lists and risk breakdown structure.
upvoted 1 times
...
ahmedSayis
2 years ago
D. Use existing prompt lists and risk breakdown structure.
upvoted 2 times
...
edusousa
2 years, 10 months ago
"What procedure could the project manager use to identify" IDENTIFY Option D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...