Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?
A.
Cross train others to reduce the SME workload.
B.
Introduce scope reductions to limit the reliance on SMEs.
C.
Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
D.
Extend the project schedule timeline to accommodate availability of the SME.
Critical deliverable indicates that the scope might not be removed/eliminated. Hence crossing training for future project would be an appropriate strategy
Cross-training might be hard to achieve if the SME is already so busy. If other SMEs were available for a cross-training program then it would be more beneficial for the project to assign those SMEs to the already delayed tasks. Also
A Cross train others to reduce the SME workload. It is better to the future.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PMI-RMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Linkedin_Dario_Conde
6 months, 2 weeks agoAhmedRashad
7 months, 3 weeks agoAzharmak
9 months, 1 week agoRehman7510
10 months agoRoyalWarrior
1 year, 2 months agoaws_guru1
1 year, 3 months agoedusousa
3 years, 3 months ago