exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 43 discussion

Actual exam question from PMI's PMI-ACP
Question #: 43
Topic #: 1
[All PMI-ACP Questions]

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.
What should the product owner do?

  • A. Terminate the project to cut losses
  • B. Review possible options and make an informed decision to cut losses based on delivered business value
  • C. Bring in experts to increase the probability of success
  • D. Continue the project, release the product without the failing feature, and fix the feature in a subsequent release
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chlaithem
10 months, 1 week ago
Selected Answer: B
A. Immediate termination: While cutting losses might seem prudent, it might prematurely discard potential value from the delivered work and may not consider alternative solutions. C. Bring in experts: While expertise can be helpful, it might be resource-intensive and incur additional costs when the remaining time and budget are limited. D. Release without the feature: This could significantly impact the product's functionality and value proposition, potentially damaging user experience and brand reputation.
upvoted 1 times
...
bcacp
1 year, 2 months ago
Selected Answer: B
Vote B, there is no additional time to do more sprints since its at the end of the project.
upvoted 2 times
...
Akhundzada
1 year, 2 months ago
Selected Answer: B
When a critical feature is not functioning as expected and the project is at a high risk of failure, the product owner should review possible options and make an informed decision based on the delivered business value. This could involve evaluating the potential impact of the failing feature on the overall value of the product and deciding whether it's better to cut losses by terminating the project or by making adjustments to salvage the value that has been delivered.
upvoted 1 times
...
Minhha3
1 year, 7 months ago
Vote B
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: B
B - correct D - this would be correct if the project couldn't be at the end. Having in mind that "a critical feature not functioning as expected", there's no time for "subsequent release" to fix this. It is "Toward the end of a project".
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: B
I would go with B. Please note that it is the end of the project (not the end of a sprint). There are no future sprints when a project is ended or has ended. To extend the project you need approvals and budget for senior management, the PO cannot make budget decisions on his own. So, in this situation B is the better answer.
upvoted 1 times
...
richck102
2 years, 4 months ago
i vote B
upvoted 1 times
...
GPena
3 years, 7 months ago
B makes more sense
upvoted 3 times
...
SARS
3 years, 9 months ago
D is the answer
upvoted 2 times
ZNFSA
3 years, 8 months ago
The project is ending and there may be no further release to fix the feature.
upvoted 6 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...