Actual exam question from PMI's PgMP
Question #: 336
Topic #: 1
[All PgMP Questions]

A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?

  • A. Execute the transition plan, and include knowledge transfer to transition Alpha support to operations.
  • B. Keep the Alpha program open until support is no longer required, then execute program closure.
  • C. Adjust Alpha's exit criteria to ensure its support is included in the Beta program.
  • D. Document the program closure procedure to ensure that resources are released from Alpha to develop Beta.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
A is the best choice
upvoted 1 times
...
[Removed]
1 year, 5 months ago
Selected Answer: A
A. Execute the transition plan, and include knowledge transfer to transition Alpha support to operations. This action ensures that the support for the Alpha software continues after the program has officially closed. The transition plan should include handing over responsibilities to the operational team who will support Alpha post-launch. This includes knowledge transfer, so the operational team understands the software and has the necessary information and documentation to maintain and support it effectively.
upvoted 1 times
...
hanyulin
1 year, 5 months ago
Selected Answer: A
A is the right answer.
upvoted 1 times
...
NawrasHamwi
2 years, 4 months ago
in Normal case, A will be the answer, in this case same team will continue working in developing the software, so same developers will make the support not the Operations
upvoted 2 times
...
Corners
4 years ago
+1. A is the answer
upvoted 1 times
...
tsangckl
4 years, 1 month ago
My answer is A. B is not the answer for sure as it is not the way to keep program open. D is not the answer, as closure procedure not make sure the operation support is going well. C I don't think it is the answer,. As Beta is another software. Alpha program is not support by Beta program.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...